=> Link to the "UNICOS Project & Roadmap" public page.

Project management structure

The management structure for the UNICOS project, documented in the EDMS:2114678 document, aims at strengthening the participation of the user’s community in the definition of priorities and the long-term evolution of the project.

The following bodies are involved:

  • The Users Meeting (UM) is a forum for information dissemination about the project and to capture users’ requests.

  • The Technical Committee (TC) is responsible for the day-to-day decisions in the UNICOS project.

  • The Advisory Committee (AC) is responsible for strategical decisions that may have an impact on the long-term evolution of the project.

  • The Project Management in BE-ICS which listens to the recommendations from the Technical and Advisory Committees and takes the final decision on the steering of the project based on the available resources..

The mandates and membership for them may be found in the document quoted above.

Scope

The project covers: the UNICOS SCADA , all uCPC baselines and templates, as well as the UAB (Unicos Application Builder).

Meetings

The UNICOS Users' Meeting is open for public; in the past this was the forum to discuss and present the plan of work and priorities (these roles have been delegated to the TC and AC meetings). The complete list of past user meetings may be found in INDICO.

The UNICOS Technical Committee (INDICO) and UNICOS Advisory Committee (INDICO), are closed forums; project management informs the users community (through UNICOS Users Meeting) about the outcome of discussions.

Roadmap

The priorities of the items in this roadmap's backlog is managed by the TC, and items are selected by the Project Management to be worked on for yearly releases of UNICOS based on the expressed and agreed priorities.

As explained in the Project Organization document (see top of the page), the final decision on the content of the Plan of Work stays with the Project Management.

The order of priorities (and list of tasks being worked on) may be changed throughout the year if demanded/agreed by the technical committee.

Plan of Work (PoW)

The current plan of work for 2020 approved by TC and endorsed by AC can be found in the following link


EDMS:2382682

Release plan for version 2020

  • 23rd November 2020. FD will produce a release candidate of UNICOS & CPC that will be tested by AP.

  • 15th December 2020. AP, after successful completion of the test catalogues and provided there are not major issues, shall give the green light to FD to proceed with release package and publication.

  • 18th December 2020. UNICOS and CPC official release be published and announced to the users.

 